3.
Identify Lot Sizing/Setup Opportunities
Present
lot size is 1000 pieces, about two day's production. This requires at
least 3-6 days finished goods and prevents daily adjustments to mix or
demand.
If
the lot size were simply cut, it would allow faster response but
additional setup time in machining would use available time. Machining
could not meet the average customer requirements.
However,
if a focused setup
reduction is made on machining and setup becomes 20-30
minutes, a batch size of 500, or even
250 is feasible. The mapping team established this as a goal, noted by a
Kaizen
Burst.
4.
Identify Potential Workcells
The
balance chart shows cycle time for each of the five process steps.
Machining and honing operations are closely balanced. cycle times for
clean/deburr, inspection and packaging are quite short in comparison.
The
very short cycle times for clean/deburr and packaging might normally
preclude them from a workcell since utilization would be low. However,
inspection and packaging are manual operations that require little more
than a workbench and hand tools. High equipment utilization is not
critical.
The
clean/deburr process is run on specialized, high-speed equipment in a
central area. If clean/deburr can be scaled
down as a manual or semi-manual operation, it can go in the cell.
This seems feasible and the team accepts that, somehow, it will be done.
It
appears that three operators can run the cell.
This is not a precise calculation. It only considers present cycle times
and ignores setup. However, for a variety of reasons, 2-3 operators is
probably feasible.
Workcells
are lot more involved than suggested here. However, our
purpose is not to finalize details but make reasonable guesses about the
general configuration. A Kaizen Burst identifies a need for
more work. |
5.
Determine Kanban Locations
With
a workcell for five processes, scheduling between them becomes a trivial
case. They will be directly linked with continuous or
small-batch flow. Kanban, internal to the cell, is unnecessary or
becomes part of the detailed cell design.
Kanban
does apply at two other locations:
The
detailed design of the kanban system is shown as a
Kaizen burst. Inventory levels are current best estimates.
6.
Establish Scheduling Methods
Kanban
and direct links now schedule all operations short term. Both the workcell
and the supplier, however, need forecasts to plan staffing
and possible changes in inventory levels. The map shows this monthly
information flow.
Purchasing
must arrange for payment. They intend to do so with monthly blanket
orders, also shown.
7.
Calculate Lead and Cycle Time.
The
final step in the Future State Map is to complete the timeline
at bottom, and calculate Lead Time, Cycle Time
and Work Time.
Results
In
this example, the mapping team estimates a Lead
Time reduction of 85% and a productivity
increase of 25%. Inventory will
decrease about 85%. Many additional, but unpredictable
benefits are also likely.
Other
VSM Topics
Present State Value Stream Mapping The Future State Value Stream Mapping Symbols The Limits of VSM VSM Software Download VSM Icons Book- Strategos Guide To VSM
Online
Interactive Seminar
Take
your learning team through the experience of mapping their own
process with an experienced facilitator. Learn the basics and
the nuance of Value Stream
Mapping, Process Mapping facilitating, and streamlining. |
|