|
A
smaller but well-known aircraft company attempted to implement Lean
Manufacturing for their machine shop and subassembly operations. The
Kaizen Blitz was their primary approach. They employed
consultants who came in with the usual panoply of edicts and
pronouncements:
-
Inventory
is evil and must be eliminated regardless of all other
considerations.
-
The
primary measure of work-cell performance is throughput time.
-
Machine
utilization is of no consequence and should be ignored.
-
Work-cells
must have a straight-through flow for all products.
-
Work-cells
must have one-piece flow.
-
Low-tech,
manual machine tools are superior to high-tech NC equipment.
-
Lot
sizes must be cut drastically.
These
edicts apply to many manufacturing situations including this
particular manufacturer's subassembly cells. Indeed, the subassembly
cells functioned quite well.
Things
did not work so well in machining. Here, a very low-volume,
high-variety product mix combined with the above beliefs brought the
following results:
-
One
Piece Flow combined with a disregard for equipment utilization
resulted in cells that were paced to the slowest operation on
each part thus reducing effective capacity.
-
Straight-through
flow precluded many parts from a particular cell. These
inconvenient parts were simply outsourced.
-
Since
Lean efforts were restricted to Kaizen Blitz' at the cells, no
effort was made to provide purchasing the tools they needed to
monitor inventories. With many more parts now being outsourced,
inventories of purchased machinings mushroomed.
|
-
Failure
to adequately implement setup reduction brought even less
capacity as lot sizes were reduced.
-
Machining
cells were initially tied to particular subassemblies rather
than families of similar piece parts. This resulted in
sub-optimum cells and limited the number of parts available to a
workcell. Many cells were starved for work.
-
Operations
were taken off of NC equipment and replaced by a series of
operations on manual machines. The multiple fixtures produced
tolerance buildups and created severe quality problems for some
items.
-
Eventually,
so many parts were outsourced and so little produced that the
shop could not cover fixed cost. This did not seem readily
apparent, however, because of the fixation on throughput time
and WIP as the only significant metrics.
The
overall result has been layoffs, higher inventories, an unprofitable
cost structure, management changes, and severe pressure from the
corporate masters.
Other
Examples
Is
The Kaizen Blitz Right For You?
Kaizen
Blitz Overdose
Kaizen
& One Piece Flow
Rationalized
Workcell Design
Workcell
Design Seminary
Historical
Note:
The
guiding beliefs discussed here derive from Toyota's JIT starting in
the early 1950's. Such beliefs were useful for Toyota and similar
manufacturers. They do not apply to all situations.
A
low-volume, high-variety machine shop is one situation where these
guiding beliefs do not apply directly. |